How long does a Single Construction Permit permit take in Mount Pleasant, Calgary?

Rolling 24 months · Sample: 73
Median days · Applied → Issued
21 days
Sample: 73 permits, last 24 months
Median days · Issued → Completed
309 days
From permit issuance to completion
City-wide median
18 days
Mount Pleasant is 3 days slower

Recent examples in Mount Pleasant

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-12339NewB2 Build2026-07-022026-08-2049$228K
BP2026-12341NewB2 Build2026-07-022026-08-2049$228K
BP2026-04195NewCraftcore Homes2026-03-182026-08-17152$479K
BP2026-14585NewWilliam Blake Homes2026-08-042026-08-1713$717K
BP2026-11811NewDiamond Peak Homes2026-06-252026-07-3035$302K