How long does a Single Construction Permit permit take in Mount Pleasant, Calgary?
Median days · Applied → Issued
21 days
Sample: 73 permits, last 24 months
Median days · Issued → Completed
309 days
From permit issuance to completion
City-wide median
18 days
Mount Pleasant is 3 days slower
Recent examples in Mount Pleasant
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-12339 | New | B2 Build | 2026-07-02 | 2026-08-20 | 49 | $228K |
| BP2026-12341 | New | B2 Build | 2026-07-02 | 2026-08-20 | 49 | $228K |
| BP2026-04195 | New | Craftcore Homes | 2026-03-18 | 2026-08-17 | 152 | $479K |
| BP2026-14585 | New | William Blake Homes | 2026-08-04 | 2026-08-17 | 13 | $717K |
| BP2026-11811 | New | Diamond Peak Homes | 2026-06-25 | 2026-07-30 | 35 | $302K |