How long does a Commercial / Multi Family Project permit take in Mount Pleasant, Calgary?
Median days · Applied → Issued
93 days
Sample: 61 permits, last 24 months
Median days · Issued → Completed
314 days
From permit issuance to completion
City-wide median
42 days
Mount Pleasant is 51 days slower
Recent examples in Mount Pleasant
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2025-12009 | New | Gold Homes | 2025-06-22 | 2026-08-06 | 410 | $1.3M |
| BP2026-08098 | New | Twin Real Estate Holdings | 2026-05-11 | 2026-07-30 | 80 | $673K |
| BP2025-08598 | New | — | 2025-05-08 | 2026-07-08 | 426 | $8.6M |
| BP2026-03248 | Improvement | — | 2026-03-03 | 2026-06-24 | 113 | $0 |
| BP2026-02913 | Improvement | — | 2026-02-26 | 2026-05-26 | 89 | $350K |