How long does a Commercial / Multi Family Project permit take in Mount Pleasant, Calgary?

Rolling 24 months · Sample: 61
Median days · Applied → Issued
93 days
Sample: 61 permits, last 24 months
Median days · Issued → Completed
314 days
From permit issuance to completion
City-wide median
42 days
Mount Pleasant is 51 days slower

Recent examples in Mount Pleasant

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2025-12009NewGold Homes2025-06-222026-08-06410$1.3M
BP2026-08098NewTwin Real Estate Holdings2026-05-112026-07-3080$673K
BP2025-08598New2025-05-082026-07-08426$8.6M
BP2026-03248Improvement2026-03-032026-06-24113$0
BP2026-02913Improvement2026-02-262026-05-2689$350K