How long does a Residential Improvement Project permit take in McKenzie Towne, Calgary?
Median days · Applied → Issued
14 days
Sample: 208 permits, last 24 months
Median days · Issued → Completed
81 days
From permit issuance to completion
City-wide median
17 days
McKenzie Towne is 3 days faster
Recent examples in McKenzie Towne
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-11202 | Improvement | Desert Sun Patios | 2026-06-18 | 2026-09-10 | 84 | $40K |
| BP2026-15678 | New | — | 2026-08-18 | 2026-09-03 | 16 | $55K |
| BP2026-14934 | Improvement | — | 2026-08-07 | 2026-08-31 | 24 | $3K |
| BP2026-15629 | Improvement | — | 2026-08-17 | 2026-08-31 | 14 | $5K |
| BP2026-12204 | Improvement | — | 2026-06-30 | 2026-08-20 | 51 | $17K |