How long does a Commercial / Multi Family Project permit take in McKenzie Towne, Calgary?
Median days · Applied → Issued
29 days
Sample: 39 permits, last 24 months
Median days · Issued → Completed
78 days
From permit issuance to completion
City-wide median
42 days
McKenzie Towne is 13 days faster
Recent examples in McKenzie Towne
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-13979 | Improvement | Tidy Life Build and Design | 2026-07-25 | 2026-09-04 | 41 | $13K |
| BP2026-11093 | New | — | 2026-06-17 | 2026-08-20 | 64 | $1.5M |
| BP2026-13575 | Unspecified | — | 2026-07-21 | 2026-08-14 | 24 | $33K |
| BP2026-10363 | Improvement | Choice Specialty Services | 2026-06-08 | 2026-08-13 | 66 | $300K |
| BP2026-10091 | New | Kamex Construction | 2026-06-04 | 2026-07-30 | 56 | $100K |