How long does a Residential Improvement Project permit take in Mayland Heights, Calgary?
Median days · Applied → Issued
26 days
Sample: 58 permits, last 24 months
Median days · Issued → Completed
134 days
From permit issuance to completion
City-wide median
17 days
Mayland Heights is 9 days slower
Recent examples in Mayland Heights
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-14843 | New | — | 2026-08-06 | 2026-09-01 | 26 | $65K |
| BP2026-15045 | Improvement | — | 2026-08-10 | 2026-08-23 | 13 | $10K |
| BP2026-13861 | Improvement | True North Concrete Cutting and Coring | 2026-07-23 | 2026-08-18 | 26 | $8K |
| BP2026-07893 | Improvement | Blue Horse Worldwide | 2026-05-08 | 2026-07-28 | 81 | $79K |
| BP2026-10186 | Improvement | Modern Block | 2026-06-05 | 2026-07-17 | 42 | $81K |