How long does a Commercial / Multi Family Project permit take in Mayland Heights, Calgary?
Median days · Applied → Issued
19 days
Sample: 10 permits, last 24 months
Median days · Issued → Completed
82 days
From permit issuance to completion
City-wide median
42 days
Mayland Heights is 23 days faster
Recent examples in Mayland Heights
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-11567 | New | Eagle Crest Construction | 2026-06-23 | 2026-08-13 | 51 | $415K |
| BP2026-11568 | New | Eagle Crest Construction | 2026-06-23 | 2026-08-13 | 51 | $329K |
| BP2026-12129 | Improvement | Epic Roofing and Exteriors Commercial | 2026-06-30 | 2026-07-24 | 24 | $300K |
| BP2026-11449 | Improvement | Legacy Kitchens | 2026-06-22 | 2026-07-15 | 23 | $44K |
| BP2026-12555 | Unspecified | — | 2026-07-07 | 2026-07-10 | 3 | $6K |