How long does a Residential Improvement Project permit take in Marlborough Park, Calgary?
Median days · Applied → Issued
25 days
Sample: 58 permits, last 24 months
Median days · Issued → Completed
51 days
From permit issuance to completion
City-wide median
17 days
Marlborough Park is 8 days slower
Recent examples in Marlborough Park
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-14887 | New | Alliance Renovations and Concrete | 2026-08-06 | 2026-09-03 | 28 | $51K |
| BP2026-15415 | Improvement | — | 2026-08-14 | 2026-08-27 | 13 | $20K |
| BP2026-14652 | Improvement | — | 2026-08-04 | 2026-08-13 | 9 | $9K |
| BP2026-13665 | New | — | 2026-07-21 | 2026-08-05 | 15 | $69K |
| BP2026-12291 | New | General Contractor | 2026-07-02 | 2026-07-28 | 26 | $56K |