How long does a Commercial / Multi Family Project permit take in Marlborough Park, Calgary?

Rolling 24 months · Sample: 11
Median days · Applied → Issued
48 days
Sample: 11 permits, last 24 months
Median days · Issued → Completed
58 days
From permit issuance to completion
City-wide median
42 days
Marlborough Park is 6 days slower

Recent examples in Marlborough Park

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-10969Improvement2026-06-152026-08-1157$50K
BP2025-22274Improvement2025-11-182026-01-1558$800
BP2025-21177Improvement2025-10-292025-11-079$10K
BP2025-16854Improvement2025-08-282025-10-2861$0
BP2025-13669ImprovementCrestview Electric2025-07-152025-09-2471$70K