How long does a Commercial / Multi Family Project permit take in Marlborough Park, Calgary?
Median days · Applied → Issued
48 days
Sample: 11 permits, last 24 months
Median days · Issued → Completed
58 days
From permit issuance to completion
City-wide median
42 days
Marlborough Park is 6 days slower
Recent examples in Marlborough Park
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-10969 | Improvement | — | 2026-06-15 | 2026-08-11 | 57 | $50K |
| BP2025-22274 | Improvement | — | 2025-11-18 | 2026-01-15 | 58 | $800 |
| BP2025-21177 | Improvement | — | 2025-10-29 | 2025-11-07 | 9 | $10K |
| BP2025-16854 | Improvement | — | 2025-08-28 | 2025-10-28 | 61 | $0 |
| BP2025-13669 | Improvement | Crestview Electric | 2025-07-15 | 2025-09-24 | 71 | $70K |