How long does a Demolition permit take in Manchester Industrial, Calgary?

Rolling 24 months · Sample: 4
Median days · Applied → Issued
10 days
Sample: 4 permits, last 24 months
Median days · Issued → Completed
81 days
From permit issuance to completion
City-wide median
4 days
Manchester Industrial is 6 days slower

Recent examples in Manchester Industrial

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-04796DemolitionTitan Contracting and Demolition2026-03-272026-03-303$0
BP2026-02743DemolitionTitan Contracting and Demolition2026-02-242026-02-262$0
BP2025-18441DemolitionAlberta Installation Group2025-09-192025-10-2334$0
BP2025-15418DemolitionAble Demolition Services2025-08-082025-08-2517$0