How long does a Commercial / Multi Family Project permit take in Manchester Industrial, Calgary?
Median days · Applied → Issued
45 days
Sample: 156 permits, last 24 months
Median days · Issued → Completed
97 days
From permit issuance to completion
City-wide median
42 days
Manchester Industrial is 3 days slower
Recent examples in Manchester Industrial
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-12388 | Improvement | — | 2026-07-03 | 2026-09-08 | 67 | $94K |
| BP2026-16454 | Unspecified | — | 2026-08-28 | 2026-08-31 | 3 | $9K |
| BP2026-15227 | Unspecified | — | 2026-08-12 | 2026-08-18 | 6 | $5K |
| BP2026-14549 | Improvement | Create | 2026-08-03 | 2026-08-17 | 14 | $10K |
| BP2026-13378 | Improvement | Soundtex Interiors | 2026-07-17 | 2026-08-13 | 27 | $27K |