How long does a Residential Improvement Project permit take in Kingsland, Calgary?
Median days · Applied → Issued
28 days
Sample: 53 permits, last 24 months
Median days · Issued → Completed
204 days
From permit issuance to completion
City-wide median
17 days
Kingsland is 11 days slower
Recent examples in Kingsland
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-08029 | New | — | 2026-05-09 | 2026-09-11 | 125 | $51K |
| BP2026-14387 | New | — | 2026-07-30 | 2026-09-09 | 41 | $154K |
| BP2026-15239 | New | — | 2026-08-12 | 2026-09-09 | 28 | $77K |
| BP2026-13433 | New | Pama Homes | 2026-07-17 | 2026-08-13 | 27 | $55K |
| BP2026-12202 | Improvement | — | 2026-06-30 | 2026-08-11 | 42 | $84K |