How long does a Commercial / Multi Family Project permit take in Kingsland, Calgary?

Rolling 24 months · Sample: 35
Median days · Applied → Issued
87 days
Sample: 35 permits, last 24 months
Median days · Issued → Completed
139 days
From permit issuance to completion
City-wide median
42 days
Kingsland is 45 days slower

Recent examples in Kingsland

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-15830Improvement2026-08-202026-09-1021$3K
BP2026-09586NewHopewell Residential2026-05-292026-08-3194$591K
BP2026-09624NewHopewell Residential2026-05-292026-08-2891$634K
BP2026-12014NewExact Ypc2026-06-292026-08-1143$809K
BP2026-11337Improvement2026-06-192026-07-1526$25K