How long does a Commercial / Multi Family Project permit take in Kingsland, Calgary?
Median days · Applied → Issued
87 days
Sample: 35 permits, last 24 months
Median days · Issued → Completed
139 days
From permit issuance to completion
City-wide median
42 days
Kingsland is 45 days slower
Recent examples in Kingsland
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-15830 | Improvement | — | 2026-08-20 | 2026-09-10 | 21 | $3K |
| BP2026-09586 | New | Hopewell Residential | 2026-05-29 | 2026-08-31 | 94 | $591K |
| BP2026-09624 | New | Hopewell Residential | 2026-05-29 | 2026-08-28 | 91 | $634K |
| BP2026-12014 | New | Exact Ypc | 2026-06-29 | 2026-08-11 | 43 | $809K |
| BP2026-11337 | Improvement | — | 2026-06-19 | 2026-07-15 | 26 | $25K |