How long does a Single Construction Permit permit take in Inglewood, Calgary?

Rolling 24 months · Sample: 17
Median days · Applied → Issued
42 days
Sample: 17 permits, last 24 months
Median days · Issued → Completed
320 days
From permit issuance to completion
City-wide median
18 days
Inglewood is 24 days slower

Recent examples in Inglewood

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-07819NewLt Custom Homes2026-05-072026-08-0489$353K
BP2026-07821NewLt Custom Homes2026-05-072026-08-0489$319K
BP2026-13865NewDatum Homes2026-07-232026-07-274$0
BP2026-07447NewMarjon Homes2026-05-042026-06-2249$0
BP2026-07627NewMarjon Homes2026-05-052026-06-2248$0