How long does a Commercial / Multi Family Project permit take in Inglewood, Calgary?
Median days · Applied → Issued
55 days
Sample: 51 permits, last 24 months
Median days · Issued → Completed
97 days
From permit issuance to completion
City-wide median
42 days
Inglewood is 13 days slower
Recent examples in Inglewood
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-13231 | Improvement | Halworth Halworth Construction Halworth Consulting | 2026-07-15 | 2026-08-11 | 27 | $35K |
| BP2026-01305 | New | — | 2026-01-28 | 2026-07-30 | 183 | $15K |
| BP2026-08361 | Unspecified | — | 2026-05-13 | 2026-07-23 | 71 | $500 |
| BP2026-04807 | Improvement | — | 2026-03-27 | 2026-07-03 | 98 | $130K |
| BP2026-05605 | Improvement | — | 2026-04-09 | 2026-06-23 | 75 | $70K |