How long does a Residential Improvement Project permit take in Huntington Hills, Calgary?
Median days · Applied → Issued
19 days
Sample: 173 permits, last 24 months
Median days · Issued → Completed
105 days
From permit issuance to completion
City-wide median
17 days
Huntington Hills is 2 days slower
Recent examples in Huntington Hills
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-14970 | Improvement | M and X Construction | 2026-08-07 | 2026-09-10 | 34 | $164K |
| BP2026-14358 | New | Garage Suites | 2026-07-29 | 2026-09-09 | 42 | $130K |
| BP2026-15476 | New | Rocky Builders | 2026-08-14 | 2026-08-25 | 11 | $56K |
| BP2026-10980 | New | — | 2026-06-16 | 2026-08-18 | 63 | $144K |
| BP2026-08248 | Improvement | — | 2026-05-12 | 2026-08-14 | 94 | $105K |