How long does a Commercial / Multi Family Project permit take in Huntington Hills, Calgary?
Median days · Applied → Issued
46 days
Sample: 15 permits, last 24 months
Median days · Issued → Completed
133 days
From permit issuance to completion
City-wide median
42 days
Huntington Hills is 4 days slower
Recent examples in Huntington Hills
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2025-24074 | Unspecified | — | 2025-12-22 | 2026-04-27 | 126 | $80K |
| BP2026-00953 | Improvement | — | 2026-01-21 | 2026-04-15 | 84 | $0 |
| BP2026-01749 | Improvement | Dong S Construction | 2026-02-05 | 2026-03-19 | 42 | $9K |
| BP2025-21115 | New | — | 2025-10-29 | 2026-03-12 | 134 | $1M |
| BP2025-20247 | Improvement | Yak Bos Landscapes and Construction | 2025-10-15 | 2025-12-10 | 56 | $50K |