How long does a Single Construction Permit permit take in Hillhurst, Calgary?

Rolling 24 months · Sample: 18
Median days · Applied → Issued
53 days
Sample: 18 permits, last 24 months
Median days · Issued → Completed
329 days
From permit issuance to completion
City-wide median
18 days
Hillhurst is 35 days slower

Recent examples in Hillhurst

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-12977NewWilliam Blake Homes2026-07-132026-09-0352$437K
BP2026-07255NewSk Real Estate Developments2026-04-302026-06-0334$488K
BP2025-20834NewD and M Custom Homes2025-10-242026-03-25152$287K
BP2025-20836NewD and M Custom Homes2025-10-242026-03-25152$287K
BP2025-09207New2025-05-162025-11-18186$0