How long does a Residential Improvement Project permit take in Hillhurst, Calgary?
Median days · Applied → Issued
21 days
Sample: 58 permits, last 24 months
Median days · Issued → Completed
123 days
From permit issuance to completion
City-wide median
17 days
Hillhurst is 4 days slower
Recent examples in Hillhurst
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-12978 | New | William Blake Homes | 2026-07-13 | 2026-09-03 | 52 | $49K |
| BP2026-14295 | Improvement | Afcg Construction | 2026-07-29 | 2026-08-18 | 20 | $44K |
| BP2026-14294 | Improvement | Afcg Construction | 2026-07-29 | 2026-08-15 | 17 | $21K |
| BP2026-09918 | Improvement | Melanson Homes and Construction | 2026-06-02 | 2026-07-14 | 42 | $5K |
| BP2025-20893 | New | — | 2025-10-26 | 2026-05-04 | 190 | $65K |