How long does a Residential Improvement Project permit take in Hidden Valley, Calgary?

Rolling 24 months · Sample: 101
Median days · Applied → Issued
16 days
Sample: 101 permits, last 24 months
Median days · Issued → Completed
79 days
From permit issuance to completion
City-wide median
17 days
Hidden Valley is 1 days faster

Recent examples in Hidden Valley

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-13960Improvement6ft8 Construction2026-07-242026-09-0846$1K
BP2026-15674New2026-08-182026-09-0316$39K
BP2026-14371ImprovementYyc Builders2026-07-302026-08-2021$10K
BP2026-14139New2026-07-272026-08-0610$51K
BP2026-09829ImprovementVaan Enterprises2026-06-012026-08-0565$335K