How long does a Commercial / Multi Family Project permit take in Hidden Valley, Calgary?
Median days · Applied → Issued
40 days
Sample: 5 permits, last 24 months
Median days · Issued → Completed
107 days
From permit issuance to completion
City-wide median
42 days
Hidden Valley is 2 days faster
Recent examples in Hidden Valley
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-08951 | Improvement | Spyder Contracting | 2026-05-21 | 2026-06-11 | 21 | $37K |
| BP2026-01537 | Unspecified | Sprouse Fire and Safety | 2026-02-02 | 2026-02-26 | 24 | $6K |
| BP2025-18794 | Improvement | — | 2025-09-24 | 2025-12-12 | 79 | $0 |
| BP2025-12729 | Improvement | — | 2025-07-02 | 2025-08-11 | 40 | $25K |
| BP2025-09433 | Improvement | — | 2025-05-20 | 2025-07-10 | 51 | $30K |