How long does a Commercial / Multi Family Project permit take in Hidden Valley, Calgary?

Rolling 24 months · Sample: 5
Median days · Applied → Issued
40 days
Sample: 5 permits, last 24 months
Median days · Issued → Completed
107 days
From permit issuance to completion
City-wide median
42 days
Hidden Valley is 2 days faster

Recent examples in Hidden Valley

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-08951ImprovementSpyder Contracting2026-05-212026-06-1121$37K
BP2026-01537UnspecifiedSprouse Fire and Safety2026-02-022026-02-2624$6K
BP2025-18794Improvement2025-09-242025-12-1279$0
BP2025-12729Improvement2025-07-022025-08-1140$25K
BP2025-09433Improvement2025-05-202025-07-1051$30K