How long does a Single Construction Permit permit take in Greenwood/Greenbriar, Calgary?
Median days · Applied → Issued
45 days
Sample: 58 permits, last 24 months
Median days · Issued → Completed
276 days
From permit issuance to completion
City-wide median
18 days
Greenwood/Greenbriar is 27 days slower
Recent examples in Greenwood/Greenbriar
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-13404 | New | Fifty6 | 2026-07-17 | 2026-09-09 | 54 | $413K |
| BP2026-14226 | New | Partners Development Group | 2026-07-28 | 2026-08-22 | 25 | $242K |
| BP2026-14227 | New | Partners Development Group | 2026-07-28 | 2026-08-22 | 25 | $242K |
| BP2026-13478 | New | Fifty6 | 2026-07-20 | 2026-08-13 | 24 | $325K |
| BP2026-08719 | New | Stealth Homes | 2026-05-19 | 2026-07-31 | 73 | $570K |