How long does a Commercial / Multi Family Project permit take in Greenwood/Greenbriar, Calgary?

Rolling 24 months · Sample: 21
Median days · Applied → Issued
59 days
Sample: 21 permits, last 24 months
Median days · Issued → Completed
156 days
From permit issuance to completion
City-wide median
42 days
Greenwood/Greenbriar is 17 days slower

Recent examples in Greenwood/Greenbriar

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-14088Improvement2026-07-272026-09-0439$90K
BP2026-14577Improvement2026-08-042026-08-2521$120K
BP2026-11849NewPartners Development Group Residential2026-06-262026-08-1449$1.1M
BP2026-12968NewPartners Development Group Residential2026-07-132026-08-1432$1.1M
BP2026-11614ImprovementKor Alta Construction2026-06-242026-07-2935$16K