How long does a Commercial / Multi Family Project permit take in Greenwood/Greenbriar, Calgary?
Median days · Applied → Issued
59 days
Sample: 21 permits, last 24 months
Median days · Issued → Completed
156 days
From permit issuance to completion
City-wide median
42 days
Greenwood/Greenbriar is 17 days slower
Recent examples in Greenwood/Greenbriar
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-14088 | Improvement | — | 2026-07-27 | 2026-09-04 | 39 | $90K |
| BP2026-14577 | Improvement | — | 2026-08-04 | 2026-08-25 | 21 | $120K |
| BP2026-11849 | New | Partners Development Group Residential | 2026-06-26 | 2026-08-14 | 49 | $1.1M |
| BP2026-12968 | New | Partners Development Group Residential | 2026-07-13 | 2026-08-14 | 32 | $1.1M |
| BP2026-11614 | Improvement | Kor Alta Construction | 2026-06-24 | 2026-07-29 | 35 | $16K |