How long does a Single Construction Permit permit take in Glenbrook, Calgary?
Median days · Applied → Issued
46 days
Sample: 34 permits, last 24 months
Median days · Issued → Completed
235 days
From permit issuance to completion
City-wide median
18 days
Glenbrook is 28 days slower
Recent examples in Glenbrook
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-11580 | New | Mountain Edge Developments | 2026-06-23 | 2026-07-27 | 34 | $244K |
| BP2026-11582 | New | Mountain Edge Developments | 2026-06-23 | 2026-07-27 | 34 | $244K |
| BP2026-04771 | New | Zias Enterprises Industry | 2026-03-26 | 2026-06-25 | 91 | $261K |
| BP2026-04773 | New | Zias Enterprises Industry | 2026-03-26 | 2026-06-25 | 91 | $260K |
| BP2026-09782 | New | Heaven Crest Homes | 2026-06-01 | 2026-06-22 | 21 | $258K |