How long does a Commercial / Multi Family Project permit take in Glenbrook, Calgary?

Rolling 24 months · Sample: 33
Median days · Applied → Issued
56 days
Sample: 33 permits, last 24 months
Median days · Issued → Completed
243 days
From permit issuance to completion
City-wide median
42 days
Glenbrook is 14 days slower

Recent examples in Glenbrook

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-07389NewSamdisha Homes2026-05-012026-07-2888$1.3M
BP2026-10078Unspecified2026-06-042026-06-2622$9K
BP2026-10195NewFortem Group2026-06-052026-06-2621$728K
BP2025-20667NewZenith Construction2025-10-222026-05-19209$304K
BP2025-20666NewZenith Construction2025-10-222026-04-17177$452K