How long does a Commercial / Multi Family Project permit take in Glenbrook, Calgary?
Median days · Applied → Issued
56 days
Sample: 33 permits, last 24 months
Median days · Issued → Completed
243 days
From permit issuance to completion
City-wide median
42 days
Glenbrook is 14 days slower
Recent examples in Glenbrook
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-07389 | New | Samdisha Homes | 2026-05-01 | 2026-07-28 | 88 | $1.3M |
| BP2026-10078 | Unspecified | — | 2026-06-04 | 2026-06-26 | 22 | $9K |
| BP2026-10195 | New | Fortem Group | 2026-06-05 | 2026-06-26 | 21 | $728K |
| BP2025-20667 | New | Zenith Construction | 2025-10-22 | 2026-05-19 | 209 | $304K |
| BP2025-20666 | New | Zenith Construction | 2025-10-22 | 2026-04-17 | 177 | $452K |