How long does a Residential Improvement Project permit take in Glamorgan, Calgary?

Rolling 24 months · Sample: 61
Median days · Applied → Issued
21 days
Sample: 61 permits, last 24 months
Median days · Issued → Completed
131 days
From permit issuance to completion
City-wide median
17 days
Glamorgan is 4 days slower

Recent examples in Glamorgan

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-14806NewCdm Developments2026-08-062026-09-0227$146K
BP2026-12103NewUmbrella Construction2026-06-302026-08-2859$127K
BP2026-15098Improvement2026-08-102026-08-2010$4K
BP2026-12638NewC and J Construction2026-07-082026-07-2113$39K
BP2026-09363ImprovementChickadee Furnace Company2026-05-272026-07-0741$221