How long does a Commercial / Multi Family Project permit take in Glamorgan, Calgary?

Rolling 24 months · Sample: 16
Median days · Applied → Issued
48 days
Sample: 16 permits, last 24 months
Median days · Issued → Completed
144 days
From permit issuance to completion
City-wide median
42 days
Glamorgan is 6 days slower

Recent examples in Glamorgan

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-02346NewOptima Developments2026-02-172026-06-18121$1.1M
BP2026-02572NewElvira Homes2026-02-202026-06-05105$860K
BP2026-08246ImprovementCalgary Egress Windows2026-05-122026-06-0423$17K
BP2026-07348Unspecified2026-05-012026-05-2322$8K
BP2026-07312Unspecified2026-05-012026-05-1413$4K