How long does a Residential Improvement Project permit take in Elbow Park, Calgary?
Median days · Applied → Issued
24 days
Sample: 77 permits, last 24 months
Median days · Issued → Completed
160 days
From permit issuance to completion
City-wide median
17 days
Elbow Park is 7 days slower
Recent examples in Elbow Park
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-15883 | New | Sandrin Construction | 2026-08-20 | 2026-09-11 | 22 | $50K |
| BP2026-14849 | New | Shift Accessibility Contractors | 2026-08-06 | 2026-08-26 | 20 | $30K |
| BP2026-15133 | New | — | 2026-08-10 | 2026-08-25 | 15 | $46K |
| BP2026-12800 | Improvement | Ld and A | 2026-07-09 | 2026-08-05 | 27 | $95K |
| BP2026-12353 | Improvement | — | 2026-07-03 | 2026-07-29 | 26 | $265K |