How long does a Demolition permit take in Elbow Park, Calgary?

Rolling 24 months · Sample: 18
Median days · Applied → Issued
3 days
Sample: 18 permits, last 24 months
Median days · Issued → Completed
101 days
From permit issuance to completion
City-wide median
4 days
Elbow Park is 1 days faster

Recent examples in Elbow Park

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-12820DemolitionCreative Solutions Contracting Services2026-07-092026-07-134$0
BP2026-08743DemolitionAndco Excavating2026-05-192026-05-289$0
BP2026-05707DemolitionCreative Solutions Contracting Services2026-04-102026-04-166$0
BP2026-02034DemolitionCreative Solutions Contracting Services2026-02-102026-02-111$0
BP2026-00533DemolitionDynamic Dirt Works2026-01-132026-01-163$0