How long does a Demolition permit take in Downtown East Village, Calgary?

Rolling 24 months · Sample: 3
Median days · Applied → Issued
53 days
Sample: 3 permits, last 24 months
Median days · Issued → Completed
4 days
From permit issuance to completion
City-wide median
4 days
Downtown East Village is 49 days slower

Recent examples in Downtown East Village

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-08062DemolitionDawson Wallace Construction2026-05-112026-05-121$0
BP2026-02563Demolition123 Boom Construction2026-02-202026-04-1453$0
BP2024-14340DemolitionCanadian Rockies Woodcraft2024-07-152025-01-02171$0