How long does a Demolition permit take in Downtown East Village, Calgary?
Median days · Applied → Issued
53 days
Sample: 3 permits, last 24 months
Median days · Issued → Completed
4 days
From permit issuance to completion
City-wide median
4 days
Downtown East Village is 49 days slower
Recent examples in Downtown East Village
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-08062 | Demolition | Dawson Wallace Construction | 2026-05-11 | 2026-05-12 | 1 | $0 |
| BP2026-02563 | Demolition | 123 Boom Construction | 2026-02-20 | 2026-04-14 | 53 | $0 |
| BP2024-14340 | Demolition | Canadian Rockies Woodcraft | 2024-07-15 | 2025-01-02 | 171 | $0 |