How long does a Commercial / Multi Family Project permit take in Downtown East Village, Calgary?
Median days · Applied → Issued
30 days
Sample: 50 permits, last 24 months
Median days · Issued → Completed
17 days
From permit issuance to completion
City-wide median
42 days
Downtown East Village is 12 days faster
Recent examples in Downtown East Village
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-09771 | New | — | 2026-06-01 | 2026-09-01 | 92 | $14.4M |
| BP2026-08607 | Improvement | Build It Calgary | 2026-05-15 | 2026-08-12 | 89 | $0 |
| BP2026-12477 | Unspecified | — | 2026-07-06 | 2026-08-06 | 31 | $68K |
| BP2026-10693 | Unspecified | — | 2026-06-11 | 2026-08-04 | 54 | $28K |
| BP2026-12544 | Unspecified | — | 2026-07-07 | 2026-07-28 | 21 | $10K |