How long does a Demolition permit take in Downtown Commercial Core, Calgary?

Rolling 24 months · Sample: 6
Median days · Applied → Issued
62 days
Sample: 6 permits, last 24 months
Median days · Issued → Completed
361 days
From permit issuance to completion
City-wide median
4 days
Downtown Commercial Core is 58 days slower

Recent examples in Downtown Commercial Core

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2024-22012DemolitionEllisDon Construction2024-10-162025-01-30106$0
BP2024-16285DemolitionRoadbridge Services2024-08-072024-10-1569$0
BP2024-21317DemolitionAble Demolition Services2024-10-072024-10-103$0
BP2024-21316DemolitionAble Demolition Services2024-10-072024-10-103$0
BP2024-16286DemolitionRoadbridge Services2024-08-072024-10-0963$0