How long does a Demolition permit take in Downtown Commercial Core, Calgary?
Median days · Applied → Issued
62 days
Sample: 6 permits, last 24 months
Median days · Issued → Completed
361 days
From permit issuance to completion
City-wide median
4 days
Downtown Commercial Core is 58 days slower
Recent examples in Downtown Commercial Core
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2024-22012 | Demolition | EllisDon Construction | 2024-10-16 | 2025-01-30 | 106 | $0 |
| BP2024-16285 | Demolition | Roadbridge Services | 2024-08-07 | 2024-10-15 | 69 | $0 |
| BP2024-21317 | Demolition | Able Demolition Services | 2024-10-07 | 2024-10-10 | 3 | $0 |
| BP2024-21316 | Demolition | Able Demolition Services | 2024-10-07 | 2024-10-10 | 3 | $0 |
| BP2024-16286 | Demolition | Roadbridge Services | 2024-08-07 | 2024-10-09 | 63 | $0 |