How long does a Residential Improvement Project permit take in Deer Ridge, Calgary?

Rolling 24 months · Sample: 40
Median days · Applied → Issued
19 days
Sample: 40 permits, last 24 months
Median days · Issued → Completed
82 days
From permit issuance to completion
City-wide median
17 days
Deer Ridge is 2 days slower

Recent examples in Deer Ridge

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-09213Improvement2026-05-262026-08-2591$0
BP2026-10978ImprovementBroch Builders2026-06-162026-07-1327$10K
BP2026-02050New2026-02-112026-06-25134$50K
BP2026-08595ImprovementInspire Buildings2026-05-152026-05-2712$40K
BP2026-05861ImprovementLeevalley Carpentry2026-04-142026-05-0521$5K