How long does a Commercial / Multi Family Project permit take in Deer Ridge, Calgary?
Median days · Applied → Issued
40 days
Sample: 12 permits, last 24 months
Median days · Issued → Completed
170 days
From permit issuance to completion
City-wide median
42 days
Deer Ridge is 2 days faster
Recent examples in Deer Ridge
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-11284 | Improvement | — | 2026-06-19 | 2026-08-25 | 67 | $40K |
| BP2026-07182 | Improvement | — | 2026-04-30 | 2026-05-22 | 22 | $5K |
| BP2025-16931 | Improvement | — | 2025-08-29 | 2025-10-07 | 39 | $85K |
| BP2025-11328 | Improvement | — | 2025-06-12 | 2025-08-26 | 75 | $100K |
| BP2025-13811 | Improvement | — | 2025-07-16 | 2025-08-25 | 40 | $10K |