How long does a Commercial / Multi Family Project permit take in Deer Ridge, Calgary?

Rolling 24 months · Sample: 12
Median days · Applied → Issued
40 days
Sample: 12 permits, last 24 months
Median days · Issued → Completed
170 days
From permit issuance to completion
City-wide median
42 days
Deer Ridge is 2 days faster

Recent examples in Deer Ridge

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-11284Improvement2026-06-192026-08-2567$40K
BP2026-07182Improvement2026-04-302026-05-2222$5K
BP2025-16931Improvement2025-08-292025-10-0739$85K
BP2025-11328Improvement2025-06-122025-08-2675$100K
BP2025-13811Improvement2025-07-162025-08-2540$10K