How long does a Residential Improvement Project permit take in Currie Barracks, Calgary?
Median days · Applied → Issued
24 days
Sample: 33 permits, last 24 months
Median days · Issued → Completed
166 days
From permit issuance to completion
City-wide median
17 days
Currie Barracks is 7 days slower
Recent examples in Currie Barracks
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-15001 | Improvement | Sw Roofing | 2026-08-09 | 2026-09-02 | 24 | $90K |
| BP2026-14127 | Improvement | Envirocrete Concrete Services | 2026-07-27 | 2026-08-07 | 11 | $22K |
| BP2026-12278 | New | Homes by Us | 2026-07-02 | 2026-07-31 | 29 | $133K |
| BP2026-07759 | Improvement | — | 2026-05-06 | 2026-07-27 | 82 | $20K |
| BP2026-10215 | Improvement | Nordstrom Contracting | 2026-06-05 | 2026-06-18 | 13 | $3K |