How long does a Residential Improvement Project permit take in Currie Barracks, Calgary?

Rolling 24 months · Sample: 33
Median days · Applied → Issued
24 days
Sample: 33 permits, last 24 months
Median days · Issued → Completed
166 days
From permit issuance to completion
City-wide median
17 days
Currie Barracks is 7 days slower

Recent examples in Currie Barracks

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-15001ImprovementSw Roofing2026-08-092026-09-0224$90K
BP2026-14127ImprovementEnvirocrete Concrete Services2026-07-272026-08-0711$22K
BP2026-12278NewHomes by Us2026-07-022026-07-3129$133K
BP2026-07759Improvement2026-05-062026-07-2782$20K
BP2026-10215ImprovementNordstrom Contracting2026-06-052026-06-1813$3K