How long does a Commercial / Multi Family Project permit take in Currie Barracks, Calgary?

Rolling 24 months · Sample: 22
Median days · Applied → Issued
92 days
Sample: 22 permits, last 24 months
Median days · Issued → Completed
61 days
From permit issuance to completion
City-wide median
42 days
Currie Barracks is 50 days slower

Recent examples in Currie Barracks

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-14198Unspecified2026-07-282026-08-2023$300K
BP2026-08058Improvement2026-05-112026-07-0252$900
BP2024-08161New2024-04-302026-04-29729$835K
BP2026-06514Unspecified2026-04-222026-04-242$3K
BP2025-12841Improvement2025-07-032026-03-26266$35K