How long does a Commercial / Multi Family Project permit take in Currie Barracks, Calgary?
Median days · Applied → Issued
92 days
Sample: 22 permits, last 24 months
Median days · Issued → Completed
61 days
From permit issuance to completion
City-wide median
42 days
Currie Barracks is 50 days slower
Recent examples in Currie Barracks
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-14198 | Unspecified | — | 2026-07-28 | 2026-08-20 | 23 | $300K |
| BP2026-08058 | Improvement | — | 2026-05-11 | 2026-07-02 | 52 | $900 |
| BP2024-08161 | New | — | 2024-04-30 | 2026-04-29 | 729 | $835K |
| BP2026-06514 | Unspecified | — | 2026-04-22 | 2026-04-24 | 2 | $3K |
| BP2025-12841 | Improvement | — | 2025-07-03 | 2026-03-26 | 266 | $35K |