How long does a Demolition permit take in Coventry Hills, Calgary?
Median days · Applied → Issued
8 days
Sample: 4 permits, last 24 months
Median days · Issued → Completed
11 days
From permit issuance to completion
City-wide median
4 days
Coventry Hills is 4 days slower
Recent examples in Coventry Hills
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-10056 | Demolition | Ovis Group | 2026-06-03 | 2026-06-16 | 13 | $0 |
| BP2026-01295 | Demolition | Titan Contracting and Demolition | 2026-01-28 | 2026-01-30 | 2 | $0 |
| BP2025-21298 | Demolition | First General Services | 2025-10-31 | 2025-12-04 | 34 | $0 |
| BP2025-20073 | Demolition | Titan Contracting and Demolition | 2025-10-14 | 2025-10-15 | 1 | $0 |