How long does a Commercial / Multi Family Project permit take in Coventry Hills, Calgary?
Median days · Applied → Issued
35 days
Sample: 10 permits, last 24 months
Median days · Issued → Completed
88 days
From permit issuance to completion
City-wide median
42 days
Coventry Hills is 7 days faster
Recent examples in Coventry Hills
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-05462 | Improvement | Persimmon Contracting | 2026-04-08 | 2026-05-25 | 47 | $198K |
| BP2026-06366 | Improvement | — | 2026-04-20 | 2026-05-14 | 24 | $90K |
| BP2025-24148 | Unspecified | — | 2025-12-23 | 2026-01-17 | 25 | $80K |
| BP2025-12428 | Improvement | — | 2025-06-26 | 2025-09-16 | 82 | $1 |
| BP2025-08700 | Improvement | Persimmon Contracting | 2025-05-09 | 2025-05-14 | 5 | $35K |