How long does a Single Construction Permit permit take in Cougar Ridge, Calgary?
Median days · Applied → Issued
99 days
Sample: 4 permits, last 24 months
Median days · Issued → Completed
411 days
From permit issuance to completion
City-wide median
18 days
Cougar Ridge is 81 days slower
Recent examples in Cougar Ridge
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2024-22168 | New | Ledgestone Signature Homes | 2024-10-17 | 2025-02-01 | 107 | $389K |
| BP2024-21531 | New | Ledgestone Signature Homes | 2024-10-09 | 2025-01-30 | 113 | $371K |
| BP2024-21525 | New | Ledgestone Signature Homes | 2024-10-09 | 2025-01-08 | 91 | $367K |
| BP2024-23004 | New | Ledgestone Signature Homes | 2024-10-29 | 2024-12-03 | 35 | $366K |