How long does a Commercial / Multi Family Project permit take in Cougar Ridge, Calgary?

Rolling 24 months · Sample: 4
Median days · Applied → Issued
56 days
Sample: 4 permits, last 24 months
Median days · Issued → Completed
275 days
From permit issuance to completion
City-wide median
42 days
Cougar Ridge is 14 days slower

Recent examples in Cougar Ridge

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-06395ImprovementButtcon West2026-04-202026-06-3071$12.1M
BP2025-10824Improvement2025-06-062025-06-2317$40K
BP2025-08468ImprovementButtcon West2025-05-072025-06-1741$2.2M
BP2024-08223Improvement2024-04-302024-09-26149$110K