How long does a Commercial / Multi Family Project permit take in Cougar Ridge, Calgary?
Median days · Applied → Issued
56 days
Sample: 4 permits, last 24 months
Median days · Issued → Completed
275 days
From permit issuance to completion
City-wide median
42 days
Cougar Ridge is 14 days slower
Recent examples in Cougar Ridge
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-06395 | Improvement | Buttcon West | 2026-04-20 | 2026-06-30 | 71 | $12.1M |
| BP2025-10824 | Improvement | — | 2025-06-06 | 2025-06-23 | 17 | $40K |
| BP2025-08468 | Improvement | Buttcon West | 2025-05-07 | 2025-06-17 | 41 | $2.2M |
| BP2024-08223 | Improvement | — | 2024-04-30 | 2024-09-26 | 149 | $110K |