How long does a Residential Improvement Project permit take in Citadel, Calgary?
Median days · Applied → Issued
19 days
Sample: 108 permits, last 24 months
Median days · Issued → Completed
81 days
From permit issuance to completion
City-wide median
17 days
Citadel is 2 days slower
Recent examples in Citadel
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-14372 | Improvement | Maxgreen Windows Siding and Roofing | 2026-07-30 | 2026-08-26 | 27 | $1K |
| BP2026-14228 | New | Argy Plumbing and Heating | 2026-07-28 | 2026-08-19 | 22 | $81K |
| BP2026-12367 | Improvement | — | 2026-07-03 | 2026-08-05 | 33 | $2K |
| BP2026-12330 | Improvement | True North Concrete Cutting and Coring | 2026-07-02 | 2026-08-04 | 33 | $7K |
| BP2023-14589 | Improvement | — | 2023-08-29 | 2026-07-22 | 1058 | $105K |