How long does a Commercial / Multi Family Project permit take in Citadel, Calgary?
Median days · Applied → Issued
41 days
Sample: 5 permits, last 24 months
Median days · Issued → Completed
79 days
From permit issuance to completion
City-wide median
42 days
Citadel is 1 days faster
Recent examples in Citadel
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-03473 | New | Kamex Construction | 2026-03-06 | 2026-05-27 | 82 | $150K |
| BP2025-18615 | New | Kamex Construction | 2025-09-22 | 2025-11-26 | 65 | $150K |
| BP2025-03177 | Improvement | Restorers Group The | 2025-02-25 | 2025-04-07 | 41 | $1.4M |
| BP2025-01319 | Improvement | Ainsworth | 2025-01-24 | 2025-02-11 | 18 | $255K |
| BP2024-19160 | Improvement | — | 2024-09-10 | 2024-10-01 | 21 | $0 |