How long does a Single Construction Permit permit take in Chaparral, Calgary?
Median days · Applied → Issued
63 days
Sample: 7 permits, last 24 months
Median days · Issued → Completed
176 days
From permit issuance to completion
City-wide median
18 days
Chaparral is 45 days slower
Recent examples in Chaparral
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-00839 | New | Stealth Homes | 2026-01-19 | 2026-04-22 | 93 | $201K |
| BP2026-01237 | New | Stealth Homes | 2026-01-27 | 2026-04-22 | 85 | $201K |
| BP2025-19797 | New | West Creek Homes | 2025-10-08 | 2025-12-22 | 75 | $483K |
| BP2025-23644 | New | Baywest Homes | 2025-12-12 | 2025-12-17 | 5 | $279K |
| BP2025-19805 | New | West Creek Homes | 2025-10-08 | 2025-12-10 | 63 | $311K |