How long does a Commercial / Multi Family Project permit take in Chaparral, Calgary?

Rolling 24 months · Sample: 5
Median days · Applied → Issued
36 days
Sample: 5 permits, last 24 months
Median days · Issued → Completed
113 days
From permit issuance to completion
City-wide median
42 days
Chaparral is 6 days faster

Recent examples in Chaparral

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-15821Unspecified2026-08-202026-08-244$2K
BP2026-09893Improvement2026-06-022026-06-1917$263K
BP2025-23831ImprovementKamex Construction2025-12-172026-01-2842$135K
BP2025-17060ImprovementDenning Enterprise2025-09-022025-10-0836$10K
BP2024-21708NewKamex Construction2024-10-102024-12-1667$135K