How long does a Single Construction Permit permit take in Carrington, Calgary?

Rolling 24 months · Sample: 334
Median days · Applied → Issued
14 days
Sample: 334 permits, last 24 months
Median days · Issued → Completed
173 days
From permit issuance to completion
City-wide median
18 days
Carrington is 4 days faster

Recent examples in Carrington

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-11671NewMattamy Homes2026-06-242026-08-1956$374K
BP2026-14587NewMattamy Homes2026-08-042026-08-1814$182K
BP2026-14586NewMattamy Homes2026-08-042026-08-1814$182K
BP2026-14424NewMattamy Homes2026-07-302026-08-1617$167K
BP2026-14423NewMattamy Homes2026-07-302026-08-1617$167K