How long does a Residential Improvement Project permit take in Carrington, Calgary?
Median days · Applied → Issued
15 days
Sample: 386 permits, last 24 months
Median days · Issued → Completed
94 days
From permit issuance to completion
City-wide median
17 days
Carrington is 2 days faster
Recent examples in Carrington
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-15945 | Improvement | — | 2026-08-21 | 2026-09-10 | 20 | $72K |
| BP2026-13117 | Improvement | — | 2026-07-14 | 2026-09-10 | 58 | $56K |
| BP2026-14666 | Improvement | Winikraftz Projects | 2026-08-04 | 2026-09-04 | 31 | $52K |
| BP2026-12403 | New | Pama Homes | 2026-07-03 | 2026-09-03 | 62 | $58K |
| BP2026-14923 | Improvement | Brown Boys Building Developers | 2026-08-07 | 2026-08-31 | 24 | $59K |