How long does a Single Construction Permit permit take in Cambrian Heights, Calgary?

Rolling 24 months · Sample: 7
Median days · Applied → Issued
21 days
Sample: 7 permits, last 24 months
Median days · Issued → Completed
330 days
From permit issuance to completion
City-wide median
18 days
Cambrian Heights is 3 days slower

Recent examples in Cambrian Heights

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-07531New2026-05-042026-05-139$0
BP2026-01408NewDouglas Homes2026-01-302026-03-1746$508K
BP2025-13667NewSwift Construction2025-07-152025-07-2914$376K
BP2025-13769NewSwift Construction2025-07-162025-07-2913$377K
BP2024-23279NewInnoflex2024-11-012024-12-1342$331K