How long does a Commercial / Multi Family Project permit take in Cambrian Heights, Calgary?
Median days · Applied → Issued
50 days
Sample: 6 permits, last 24 months
Median days · Issued → Completed
93 days
From permit issuance to completion
City-wide median
42 days
Cambrian Heights is 8 days slower
Recent examples in Cambrian Heights
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-02883 | Improvement | — | 2026-02-25 | 2026-07-16 | 141 | $2K |
| BP2026-01466 | Improvement | — | 2026-01-31 | 2026-02-27 | 27 | $180K |
| BP2025-19295 | New | — | 2025-10-01 | 2026-01-30 | 121 | $944K |
| BP2025-06890 | Improvement | Syncon Management | 2025-04-17 | 2025-06-11 | 55 | $250K |
| BP2025-09656 | Improvement | — | 2025-05-22 | 2025-06-10 | 19 | $30K |