How long does a Single Construction Permit permit take in Brentwood, Calgary?

Rolling 24 months · Sample: 4
Median days · Applied → Issued
107 days
Sample: 4 permits, last 24 months
Median days · Issued → Completed
178 days
From permit issuance to completion
City-wide median
18 days
Brentwood is 89 days slower

Recent examples in Brentwood

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-07315NewUltimate Renovations2026-05-012026-09-02124$236K
BP2026-01300NewWinter Green Homes2026-01-282026-04-2789$766K
BP2024-25144New2024-12-022024-12-3129$0
BP2024-07823NewMiter Renovations and Design2024-04-262024-09-25152$327K