How long does a Commercial / Multi Family Project permit take in Brentwood, Calgary?
Median days · Applied → Issued
41 days
Sample: 40 permits, last 24 months
Median days · Issued → Completed
107 days
From permit issuance to completion
City-wide median
42 days
Brentwood is 1 days faster
Recent examples in Brentwood
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-06806 | New | Amplitude Development | 2026-04-24 | 2026-08-31 | 129 | $604K |
| BP2026-07896 | Improvement | — | 2026-05-08 | 2026-08-13 | 97 | $825K |
| BP2026-07483 | Improvement | — | 2026-05-04 | 2026-06-11 | 38 | $60K |
| BP2026-02553 | Improvement | Restorers Group The | 2026-02-20 | 2026-03-16 | 24 | $178K |
| BP2025-21842 | Improvement | — | 2025-11-11 | 2026-03-12 | 121 | $3M |