How long does a Residential Improvement Project permit take in Braeside, Calgary?

Rolling 24 months · Sample: 57
Median days · Applied → Issued
19 days
Sample: 57 permits, last 24 months
Median days · Issued → Completed
92 days
From permit issuance to completion
City-wide median
17 days
Braeside is 2 days slower

Recent examples in Braeside

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-15406Improvement2026-08-132026-09-1129$65K
BP2026-15824Improvement2026-08-202026-08-288$4K
BP2026-12876NewHaven Works2026-07-102026-07-2919$150K
BP2026-10249Improvement2026-06-052026-07-1540$5K
BP2026-08167ImprovementT2k Construction2026-05-112026-05-2918$28K